Industrial Park 100% Complete

Project Summary: The project is to establish a new fully served municipal industrial park with installation of public infrastructure (city water, sanitary sewer and streets). In addition, the EDA wrote and is administering state and federal grants to help defray a portion of the $2.4 million infrastructure cost.

Latest News: 22 September 2011

“Energy Park” is now 100% complete. This summer Industrial Boulevard between Michigan Street and Impressions, Inc. was reconstructed and a second “lift” of bituminous was added to both Hackbarth Street and Benjamin Avenue in the new Industrial Park. Also, water and sewer service was extended to a 3.09 acre lot in the southwest corner of the industrial park, making it ready for development.

NEXT STEPS:

The EDA is in the process of closing out the federal EDA grant so the remaining $238,955 can be collected by the city. Also, the EDA will work on closing out the State of Minnesota “Business Development Public Infrastructure” grant and pull in that $250,000.